The process-verbaal set out the duty to provide a gross-wage calculation. Review
Public evidence report · employment dispute · Netherlands
Employment case connected with Intrixo B.V.
The report describes a case concerning an NBBU Phase 4 agreement for 32 hours per week, wages, deductions and performance of the Rechtbank Den Haag process-verbaal of 12 March 2024. It organizes documents, calculations, correspondence and institutional responses.
Five key facts
Each point leads to a safe public description of the underlying material.
An indefinite NBBU Phase 4 agreement, not an on-call contract. Review
Advance paid on 18 March 2024; separate from the gross-wage calculation.
Expiry of the two-week period stated in the process-verbaal. Timeline
Disciplinary decision held privately; an anonymized description is public.
Key events
A concise route from the start of the calculation period to the report update.
Starting date of the required gross-wage calculation.
NBBU Phase 4 agreement begins.
Calculation duty and advance.
EUR 5,000 transfer and expiry of two weeks.
The result changed after errors were raised.
Part of the complaint upheld according to the held decision.
Changing calculation results
Successive working results, not a final amount established by a binding decision.
First version with an incomplete document set.
Second version; documentation still incomplete.
Later version; not a complete final balance.
The report’s central question
Can the complete document set demonstrate that gross wages due from 6 May 2022, deductions, bank payments and the final balance were correctly calculated? The report presents material for independent verification and does not replace a decision by a competent authority.